on 05-31-2011 4:15 PM
Hello,
I want to use co-products in a production order with the following apportionment structure:
Material X: 95 (principal material)
Material Y: 5 (co-product)
In the production process, the actual ratio produced however is 90-10!
I have the following questions:
1) Upon settlement of the order, is there a way in which SAP can reflect the real apportionment (90-10) instead of the one
defined in the material master (95-5)? Is there a config or user-exit one can use to accomplish this?
2) What unit of measure is SAP taking into acount in the aportionment structure? Base unit of measure?
Thanks for any reply.
Aart
Hi,
It may be possible to change it in the production order, Header -> Settlement rule. Costs are aportioned based on the percentages in the settlement rule, I think no unit of measure has any effect on the process.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.