on 05-31-2011 7:13 AM
Hi ,
In template roll out projects , could you please suggest what all plant specific configuration in QM needs to be taken care?
The processes to be there are - Quality Inspection & Quality Notification. I did not find any plant specific setting for these two processes and it seems that the configuration already there can be used for the new plant.
As per my understanding, there will be not much of configuration to be done except for basic setting at plant level. ( since all the processes will be same and no additional setting will be required apart from the plant specific settings).
Looking forward for your inputs.
Thank you !
Regards.
Yes Once you cover basic setting in QCC0 ,don't need much to do in rest as most of the things are already exists and maintained at client level .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.