Extending how far in advance I can schedule using CM21

I am using CM21 and When i scroll accross the screen, I can only go up to 9/28/2011 to put the orders. I want to extend this date 2 months more. What transaction do I need to be in to extend the time frame I can schedule orders on?



Dear Rashad,

In CM21,check under Menu-->settings-->time profile and I assume in your system the setting must be max no of days from

the current day is 120 days.(4 months).Now check the config setting for this time profile or assign some other time profile in

CM21 and check the same.



Edited by: Mangalraj.S on May 31, 2011 11:39 AM