on 05-31-2011 6:34 AM
Dear Sir,
I am facing problem during invioce verification. when we are going to similuate the miro system show the error message.
Maintain the acct key and accruals/provisions in the calculation schema
Message no. M8434
Diagnosis
The system cannot determine an account for the delivery costs.
Procedure
In Customizing for Purchasing, you maintain the activity Define Calculation Schema in Conditions -> Define Price Determination Process:
Proceed
If you want to settle delivery costs, define the account keys for the clearing account and provisions account in the calculation schema. The system can then determine the appropriate G/L accounts.
1. Select the calculation schema used
2. Doubleclick the node Control data in the tree.
3. Maintain the account key for the condition types in the schema.
For example, for condition type freight absolute (FRB1), enter account key FRE and the account key for provisions FR1.
Thanks.
Hi
You have any delivery cost condition in PO ?
If yes,then value of this condition is inventoried or goes to G?L account ?
check your condition in spro -MM -purchase -condition-define price determination process-define condition
check here you mark accrual for your condition on tab control data 2
If yes ,the same maintain account key and accrual key for this condition in your pricing procedure
in same path define calculation schema
Regards
kailas ugale
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
solve by account key assign.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Please maintain acccount key in pricining procedure
Regards
AKM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Solution in question itself.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If u r facing this error, it would have come while creating the PO itself.
Goto M/08 select the schema against the freight condition give the Acct & accrual key FR1
Then in OBYC against FR1 give the G/L cct & save & post the MIRO
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If you have planned some delivery cost or freight in PO and selecting option "Goods/Services+Planned Delivery Cost" in MIRO then check whether following has been maintained;
M/06 - "Accrual" indicator active for delivery cost or freight condition type under "Control Data 2" Subscreen
M/08 - Accrual "FR1" has been maintained for delivery cost or freight condition type
OBYC - Freight Clearing Account has been assigned to Account Key "FR1"
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.