on 05-31-2011 3:50 AM
Hi Gurus,
We now open our system, we are uploading material master and initial stock upload. For costing run(Product costing run) it will take two months.
i need your advise can i run costing run for Material ledger, is there any impacts.
Thanks and regards.
Ramesh.
Hi Ramesh ,
I hope you clearly understand the purpose of ML.. ML is for actual costing and Costing Run is for plan cost estimate ..
So , after you finish your costing run.. you will start posting your actuals ..
Then in month end , you will require to roll -up the variances to COGS and Inventory to get the actua cost and this is done using the Material Ledger run .. CKMLCP..
Hope it clarifies..
Regards
Sarada
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.