Hi Guys,

i've tried searching in the forum before posting the thread but i did not find any useful answer for my case.

hope you can help.

i have done an order with material xxx, availability check carried out.

material has unrestricted use of 1230 kg.

the deliver should be don for 60 kg.

when i got to deliver the order system tells me that only 0 kg form material xxxx are available.

i've check md04 and available qty is 1230 kg.

MMBe available qty is 1230 kg.

in CO09 i found rec/reqd qty 1230 but 0 qty in ATP quantity.

i went again on the order, re-done the availability check but nothing change.

any idea?

thanks

C.

Accepted Solutions (1)

Accepted Solutions (1)

Lakshmipathi
Active Contributor
0 Kudos

Check in material master MRP view what is maintained for the following fields

a) MRP Type

b) GR Processing Time

c) Planned Deliy.Time

Finally, go to OVLZ, select your shipping point and check what is maintained for Pick/pack time wrkdys

thanks

G. Lakshmipathi

Former Member
0 Kudos

Hi,

In MRP and ovlz all is maintained.

in MMBE i have this situation,

Unrestricted use 1.204,700

Qual. inspection 904,600

Reserved 2.049,000

Sales orders 60,000

all the other field are 0

any ideas?

Lakshmipathi
Active Contributor
0 Kudos
Qual. inspection 904,600
Reserved 2.049,000

The above should also be zero.

thanks

G. Lakshmipathi

Former Member
0 Kudos

Hi,

so if i have 1204 kg in unrestricted that are not taken into count because there are 2049 kg of material reserved, is that so?

how can i reduce them to 0?

for quality inspection is ok i know, but for the reserved?

thanks

jpfriends079
Active Contributor
0 Kudos

Hello

In MD04, Check the details of

Sales orders 60,000

against the material.

And also confirm delivery date in sales order - schedule line

Regards

JP

Former Member
0 Kudos

the delivery date is confirmed, and the sales order in MD04 is the one is causing problem.

i really do not know where to look. this material is an HALB and used also for production.

may be i will change the message into a warning one and then when delivery is done back to error.

but this will be my last chance.

any other idea?

Answers (1)

Answers (1)

moazzam_ali
Active Contributor
0 Kudos

hi

did you checked in MMBE in schedule for delivery quantity. Please check whether there is any quantity in schedule for delivery in MMBE