Please, could you help me at the follow:
We have the material / Plant that have component split, for exemple: Elements 05, 11, 12, 18, 19...etc.
We won't use the element 11 anymore and we need to transfer the balance from element 11 to 18.
Could you tell me how I can do it?
Thanks,
Rosana.
Hi
There is no mechanism of such a transfer...
You need to change/update the Cost Comp Str in OKTZ and shift the cost elements from 11 to 18
Then, run a CK11N again.. The cost will be transferred to 18...
You cant shift the components from 11 to 18 and yet retain the same cost estimate
br, Ajay M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Ajay!!
Thank you very much for your return.
Some people told me it is possible to transfer without change the configuration.
Your answer I agree, but what do you thing we wait some other sugestion, maybe there is some other way..
Could you tell me some comments or some body has some other suggestion?
Thanks again,
Rosana.
Hi,
it works like Ajay explained.
All cost estimates before the OKTZ change remain in the old cost component structure, after the change the new cost estimates are stored using the new cost component structure.
Thats the reason why a SAP message like "You cannot compare cost estimates after changing cost component structure" pops up when you save the OKTZ changes.
Best regards, Christian
Hi
I would be interested to know if there is any such option available..
Aux Cost comp split is a functionality which can be used to map two cost comp into one.. But I dont know if it will work once the cost is released... as far as i know, it works when its there at the time cost is released
br, Ajay M
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.