on 05-30-2011 8:58 AM
Hi Experts:
I have created a process order, and used Recipe Group A which has no resource in it, when I do CORK for it, there is no 101 posted. And then I created a new Recipe Group B which has resource in it, when do CORK, there has 101 posted.
Would you please tell me why? I searched in SDN and checked control key in Recipe Group, but cnanot find out the root cause.
Thank you in advance.
Richard
Hi,
I hope u have used the same control key for both of the scenerios
When the resource is not defined then u need to define an default resource to be taken in SPRO
Please check that
Regards,
Sravanthi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check in operation contorl key defination if Automatic GR is marked for it, then only GR is posted automatically at the time of confirmation .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.