Hi Experts:

I have created a process order, and used Recipe Group A which has no resource in it, when I do CORK for it, there is no 101 posted. And then I created a new Recipe Group B which has resource in it, when do CORK, there has 101 posted.

Would you please tell me why? I searched in SDN and checked control key in Recipe Group, but cnanot find out the root cause.

Thank you in advance.

Richard

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

I hope u have used the same control key for both of the scenerios

When the resource is not defined then u need to define an default resource to be taken in SPRO

Please check that

Regards,

Sravanthi

former_member186193
Active Contributor
0 Kudos

Dear,

Check if you are using the same control key for both the operations if not then check that if auto GR is marked in both the control key.

Hope it will help.

Regards,

Alok Tiwari

Former Member
0 Kudos

Hi,

Check in operation contorl key defination if Automatic GR is marked for it, then only GR is posted automatically at the time of confirmation .