Primary cost planning other than object currency

former_member438773
Participant
0 Kudos

Dear All,

I have maintained my controlling area curreny and Cost center object currency as USD. Now As per my user requirement i need to do primary cost planning using KP06 in SGD currency. Please help to provide your suggestions. Is it possible to select currency field in KP06 primary cost planning? Moreover i donot want to change cost center objec currency from USD to SGD.

Thanks & Regards

**********************

Kumar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

change your Planing layout key figures as Object Currency and add your transaction currency in General data selection and post your budget .

satish

former_member438773
Participant
0 Kudos

Dear Satish,

Thanks a lot for your quick and immediate response. I will get back to you very soon with the results.

Thanks & Regards

***********************

Kumar

former_member438773
Participant
0 Kudos

Dear Sathish,

Can you please let me know what variable do we need to maintained for currency field.

Thanks & Regards

*************************

Kumar

Former Member
0 Kudos

create a new varieable or use directlty the currency SGD.

satish

Answers (1)

Answers (1)

Former Member
0 Kudos

HI,

the planning layout change for primary cost happens in KP66.

Ensure that the exchange rate type / date you need from planning currency to CO-Area currency is maintained in CO version definition.

BR Christian