on 05-30-2011 6:31 AM
Dear All,
I have maintained my controlling area curreny and Cost center object currency as USD. Now As per my user requirement i need to do primary cost planning using KP06 in SGD currency. Please help to provide your suggestions. Is it possible to select currency field in KP06 primary cost planning? Moreover i donot want to change cost center objec currency from USD to SGD.
Thanks & Regards
**********************
Kumar
Hi
change your Planing layout key figures as Object Currency and add your transaction currency in General data selection and post your budget .
satish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
the planning layout change for primary cost happens in KP66.
Ensure that the exchange rate type / date you need from planning currency to CO-Area currency is maintained in CO version definition.
BR Christian
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.