Hi Experts,
We are using external number while creating the project in cProject.
In DPR_PROJECT Table it updating the same number in both fields (GUID & PROJECT_ID).
Example: If I put the "2000" as project number. If I go and check in table GUID & PRJECT_ID both are 2000, 2000).
Please tell me is there any way I can see the Project GUID.
Raj.
Hi Rajesh,
In SE16 while viewing the data, go to settings -> user parameters, uncheck the Check conversion routine.
Then, you can see GUID in DPR_ATTRIBUTES.
Regards
Amit