on 05-29-2011 12:35 PM
Hi all,
I tried to find out the reason behind the material price difference I am getting by clicking *COST ESTIMATE* in KKF6N and the price in CK11N . In KKF6N I am getting the price 500 and while doing CK11N I am getting 2000. please let me know how price is being calculated in both the screens.
Material is -- HALB
STD Price in Material master -- 200
moving price -- 50
stock -- 20
Costing variant in CK11N --- PPC1
Costing variant in KKF6N --- YPRM Premilinary PCC
Regards
Kumar
Hi,
check both costing variants used. Looks like the valuation variant within the costing variant uses moving averagre price in KKF6N and standard price in CK11N to valuate the material quantity.
Best regards, Christian
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check the sequence of price selection in both the variant PPC1 and YPRM. One must be according to standard price and other must be moving price
Regards,
Divraj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.