Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A



I have a material with three operation in production and third operation is milestone confirmation

but in qm area second operation and third operation there is inspection is assigned in routing

Now qm guy rejected all characteristic and hence his UD become rejected

but even though system allowing confirmation in CO11N

how we can block this confirmation if QM inception UD is rejected



I presume that you are talking about 03 inspection type.Please note that there is no relation between 03 inspection type UD & confirmation of production order.That's the std one.

Apart from that you can use user exit

CONFPP05 PP order conf.: Customer specific enhancements when saving !!

0 View this answer in context
Not what you were looking for? View more on this topic or Ask a question