on 05-27-2011 3:42 PM
Hi,
I have the following task:
- Jobchain A in SAP system 1 raises EVENT E1
- Jobchain B in SAP system 1 raises EVENT E2
- Jobchain C should run after A and B in SAP system 2.
Jobchain A and B are defined in isolation group I1.
Jobchain C is defined in isolation group I2.
Where and how do I have to define the EVENTs.
We have a full demo version.
Thanks.
Br
Günne
Hi Günne,
The main idea of isolation groups is that there are no dependencies between objects/jobs/... in different isolation groups.
So the job chains need to be in the same isolation group.
Kind regards,
Anton Goselink.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.