on 05-27-2011 12:51 PM
We have a process of getting "Commitment dates" from Vendors against our Required delivery dates
This commitment dates have to be uploaded in system
I am trying to do the same by LSMW
Is there any T-code in which I input specific PO number , Item no and Schedule number and the Stat.Delivery date can get changed.
There is no transaction where you can enter "specific PO number , Item no and Schedule number and the Stat.Delivery date can get changed"
Users do this activity in ME22N, in case of batch inputs you better make use of ME22 as the N-transactions are not designed for batch input.
Alternative you can use BAPI technique.
I hope you dont mix some SAP terms.
Commited dates are usually entered in Confirmation tab, here you can make use of IDOCs.
Stat. Delivery date is used for vendor evaluation only, a change in this field does not effect your planning, so nobody will know about a new committed date if you enter it here.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
10 | |
9 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.