Dear Gurus,

While customizing heuristic, there is one tab Order internal relationship which is explained in SAP help as Time relationship between two activities that belong to different operations of an order.

Its customizing options are 1.) Do not consider, 2.) Consider in propogation range, 3.) Always consider.

Can somebody please explain the significance of the options given for this tab for a REM scenario.

-Vinay

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

Thanks Nanda.

In a nutshell, i can say that

1.) if i want dependent demand to be considered while doing planning for its successor shop/operation then i should choose always consider or consider in propagation range(to choose min & max intervals as well in planning).

Any business scenario where we will choose do not consider?