on 05-27-2011 11:45 AM
Dear Experts,
I need amend Ad hoc query to be able to report on Expected End MPP Q0088-EEMPP, It is not a standard field in the infotype for SE16 or SAP Query/Ad Hoc. We need to be able to query off this field. Can someone please point me in the right direction about how to get the calculated value from this field added to queries, or what code is needed.
I have created an additional field in SQ02, i probably need code to make it fetch the data
thanks
haji
Hi,
Please take a look at standard function module HR_GBSMP_MPP_DATES. It returns the expected end date.
Hope this helps.
Donnie
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.