Missing Components in Production Order

Hi,

We have a Production Order for the FERT Material. There are say 5 components in the BOM of the FERT material. These 5 components are also assigned in the routing of the FERT Material. Now we had created the Production order by converting the Planned order.We had completed the confirmation and then settled the order. Now when we checked the components consumption, we can see that only 4 components are consumed instead of 5 components. Can anyone say what could be the reason why the 5th compoinet used. Do we have a workaround to issue the 5th component manually to the Production Order so that we can reverse the variance due to this missing component.

Appreciate your valuable suggestion.

Thanks in advance.