cancel
Showing results for 
Search instead for 
Did you mean: 

MRP Descripency

Former Member
0 Kudos

Hello,

This issue is related to MRP.

I have a material AC0001 which is a FERT Material and is produced inhouse.

It has MRP Type PD. In MRP 2 screan in the scheduling tab the In-house production is 5 days and the GR Processing time is 1 day.

The stock is Zero and there has a require which comes for 2 numbers.

For example, for material AC0001, I took the first MRP run on 5/17/11, but the first planned order created is for 5/11/11, which is in the past. Why would MRP propose a planned order in the past?

The answer to this is system is doing backward scheduling by considering inhouse production time of 5 days....generally system doesn't allow the dates to go in the past unless you do the customizing and make the system to allow scheduling in the past in the MRP parameters in SPRO.

The second portion of my question is, for the same material AC0001, the second MRP run is from 5/18/11 .On that day, planned order created has a date of 5/10/11, one day before than the previous date. Why would this happen?

Thanks & Regards

Nilesh

Accepted Solutions (1)

Accepted Solutions (1)

former_member184655
Active Contributor
0 Kudos

Dear Nilesh,

Check your scheduling parameters in OPU5,whether start in the past is defined for some days.

Regards

Mangalraj.S

Answers (4)

Answers (4)

Former Member
0 Kudos

Yes the Check was active for the start date in the Past.

Issue has been resolved

dhaval_choksi3
Active Contributor
0 Kudos

Hi,

What are the requirement dates in both the cases?

As said by other expert, check shceduling parameter for plan orders in opu5.

Regards,

Dhaval

Former Member
0 Kudos

Hi Sir,

In your case,the total RLT time is 06 Days(In -House production time plus Gr processing time) .For the planne dorder to be generated to be in past looks into the SPRO.Please checkm in OPU5,in "Sechduiling control for detailed Sechduiling" is BACkward.Also please check inplant parameters "OPPQ", for that plant "Start in Past is active or not.

For the second query,Since the planned order is being created a day before the previous day, it may be possible that there may be two days holiday.That is the only reason seems

to be

Thx

Anupam1143
Active Contributor
0 Kudos

Hi

Check in OPU5 for scheduling planned oreder whether you have selected scheduling type as Backwards also check in OPPQ whether you have selected Start in past check box for your plant.

for your second question check in SCAL whether youi have defined saturday and sunday as working day or not.

Regards

Anupam Sharma