on 05-26-2011 6:34 PM
Dear PP Gurus,
In tcode md61 when I create PIR, sundays are excluded from planning(sundays are not displayed), but my factory calender has sunday as working day.(factory calender in work centers). Please guide me to get through this issue since sundays are working days for our clients.
Thanks
Sunanth V.Narayan
dear friend,
you could do the following checks:
1.
spro->enterprise structure->definition->def,copy,del,check plant->define plant
have a look at your plant and find out the Factory clendar;
run SCAL and check out that factory calendar : look at workdays and also check out the Special rules
2.
goto material master (for your plant) tab MRP2 and look at Planning calendar (if it is set).
run MD27 and make sure periods are correct
good luck!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Check the planning calender assigned to material in MRP2, eithr you can do change in planning calender thru MD26 by including sundays in planning calender or just remove the planning calender from MRP2 view , it will be then according to factory calender.
Check and revert
Regards
Anupam Sharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.