Preventive maintenance issues

Dear PM Experts,

Please help me in solving those issues:

1) My client skipped a cycle in maintenance plans the cycle start was at 27/10/2010 then he restarted the cycle but with an earlier date in like 2006, when he restarted the cycle the system planned orders from 2010, why did the system do this ? the logic is either to call orders from 2006 ( less probability) or start and call orders from now on ! please tell me the reason for this and tell me what to do if i want to restart a cycle ?

2) after restarting a cycle i get the status 'scheduelling saved to call ' how to make the system call automatically w/o entering in every plan and save it?

3) if there is a coming order ( still not called) and i want to shift it alone without shifting the orders after it how can i do this?

also how to shift the order and the orders after it?

4) if i added a new operation and anew maintenance package to a task list will this be scheduelled with maintenance plan normally or i have to do another thing?

Very Much Thanks in advance