Dear All,
I required a help regarding one MRP Scenario is like,
FERT / Component / Qty
600061 A 5
600062 B 5
600063 C 10
600064 D 15
There is one base material, named E from that A , B , C ,D made.
On MRP run, I want to generate consolidate requirement in E only, for ABC+D.
In abo
To my understanding "E" is the component for all the materials "A", "B", "C", & "D". with diferrent quantities.
If you maintain indiviual collective " 2 ". then you will the total requirements for the mateial "E", based on the reuqirements for "A", "B", "C", & "D".