cancel
Showing results for 
Search instead for 
Did you mean: 

schedule lines - commited quantity

milascon_daniel
Participant
0 Kudos

Hi experts,

in our system we have sales orders with purchase requisition and purchase order (procured externally). Every vendor have planned delivery time in days (XK03 Purchasing data)

when i make a sales order, the system include weekend days in delivery time calculation. It's possible to exclude weekend from delivery time calculation?

Example:

i create a sales order at 26.05.2011.

material should be procured externally from vendor 10000; vendor 10000 has 4 days for planned delivery time.

system should propose 01.06.2011 as commited quantity ; without weekend

but now, in our system, SAP propose 30.05.2011 as commited quantity date.

It's possible to exclude weekend from delivery time calculation?

thank you.

Accepted Solutions (0)

Answers (2)

Answers (2)

Shiva_Ram
Active Contributor
0 Kudos

Add the relevant factory calendar in the customer master->General data->unloading points. You can find the list of calendars, that are assigned with working-non working days in t.code SCAL.

Regards,

milascon_daniel
Participant
0 Kudos

in customer master we dont have unloading points at GEneral data tab

jpfriends079
Active Contributor
0 Kudos

Hello

Take use of

- Planned Deliv. Time

- Planning calendar

in your material master - MRP2 Tab

Thanks & Regards

JP

milascon_daniel
Participant
0 Kudos

material doesn't have MRP2 tab