MRP run problem

Hai All.

I have material A having BOM with component as material B along with others. Again now material B is having material C as component along with others. Now I have run the MRP for material A. Planned orders created for A, B and C. i have checked in MD04 of these materials. It is OK. Now when I am converting the planned order of A to production order system is giving the error as First execute planning run (multi-level) for material C. But already Planned order is there for this material. This is collective orders scenario and B and C are defined with Special Procurement as 52.

Kindly help me why this error is coming and how to resolve the same.



carry out MD02 for material C and check if it works.