Cost Center Hiearchy not updated by infoPackage in a process chain

I have a cost center hierachy in a BW system with an infoPackage to update it in a process chain. If the cost center hierarchy is changed in the source system, it is not updated in the BW system (the process chain is scheduled daily). It is only updated if I start the infoPackage manually.

I have checked the infoPackage in the PC, and that there is a Hierachy/Attr. Change Run scheduled after loading it (the PC shows as being successful each time).

Former Member
replied

check that in the save hierarchy variant in your process chain, on the lower part you flag the checkbox : 'activate hierarchy after loading or mark for activation'