capacity evalution

Former Member
0 Kudos

Dear Guruji

we are COR1 to create process order in SAP.During creation of process order below message is appear

No reqmts/caps exists or not relevant to finite scheduling

what is change we have to do to remove this message?

we have also problem in capacity evaluation in T-code CM01.it saws only planned order capacity but our most of process order create directly by COR1.so what is procedure or and steps we have to change to see total capacity evaluation of planned order & process order in resources

Thanks

Pankaj Kapadia

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

If you are done with both of the solutions provided by the gurus, then check two things-

In work centre(CR12)-check box- relevant to finite scheduling

In case of conversion-

MRP Run(MD02)-MRP control parameters-scheduling-1(Determination of basic dates for planned orders)

Please check and revert.

Regards

Chandra

former_member184655
Active Contributor
0 Kudos

Dear Pankaj,

Check the configuration settings in OPU3 and OPU5,whether check box for generate capacity reqmts is included.

Check whether the control key assigned in the operation is relevant for scheduling and capacity reqmts and ensure proper

formula's has been maintained.

Check and revert.

Regards

Mangalraj.S

Former Member
0 Kudos

Hi,

For each process order type & plant combination for which you want to generate Capacity Requirements maintain following configuration setting :

Go to OPUZ (Scheduling Parameters) : Select Plant & order type & production scheduler as * ---> Under Detailed Scheduling tab opposite SelID : Detailed two check boxes are there : Scheduling & Generate Capacity Reqs. maintain tick in that.

With this settings, capacity requirements will be generated.

Hope this helps.

Regards,

Tejas