We have SRM 5 system which is dual stack. However, there is some inconsistencies in terms of SP level for the abap stack and the java stack.

ABAP stack is updated to SPS level 15. However, java stack is not updated and its at Old SPS06 level

We are now going ahead with applying stack from SPS 16 to 18. We would like to know how to go ahead with the java stack since its not at level SPS15.

Can we apply as below :

1) Kernel upgrade + SPS 16-18 for ABAP stack

2) Once that is finished - SPS 07 to SPS18 for JAva stack for SAP Netweaver 7.0 ?