Plant is changed when PR transfered to SRM

Former Member
0 Kudos

Hello SRM guys,

Our project implement Plan driven scenario. But we find one problem, when PR is transfered to SRM to create SC, Plant and storage location are changed. Example: The original PR plant is 2001, but after transfered to SRM as SC, the plant in SC is changed to 1001.

Any one solve this problem?

Thaks.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello Justin,

When we faced this issue, it was due to XI user attribute. The plant was getting updated in SC from XI user default. SAP provided the OSS note for this.

Which SRM version you are using?

Also, check if you have any DOC CHANGE implementation, which is causing this.

Hope this helps.

Ashutosh

Former Member
0 Kudos

Hi, ASHUTOSH, thanks for your response.

We are using SRM 7.0. Could you tell me the note number about this? I search notes, but dont found it .

About change badi, our implemenation dont change the plant field.

Former Member
0 Kudos

Hello Justin,

OSS Note 1344254: Plant & Storage location from PR gets overwritten in SRM SC.

Hope this solves.

Ashutosh

Answers (1)

Answers (1)

Former Member
0 Kudos

Assign PI user all used company codes.