Sched. Collective Order


if I have a collective order one parent order (A) and three child orders (B,C,D). At order start the order start dates and finish dates are alligned.

My question is, if I get a delay in child order B, should the parent order A automatically moved out if I reschedule the collective order due the later finish date of the child order ?

In our system the parent order won´t be rescheduled, are there settings to enable this ?

Thanks in advance



I should think that a collective order is scheduled as an entire linked structure. If this does not happen in your system, you need to review customization settings for scheduling, and also routing definitions.