problem with process chain

Hi All,

We are using BW 3.5 version and we have created a process chain and included an event in the chain, so when the event raises, the process chain is triggered (so, basically its an event based chain)

The event will be raised thru a Z transaction in BW only... so, when one executes the Z transaction , the event raises and it triggers the PC..

Now the problem is, we have 2 users A and B

if user A uses the Z transaction, event raises and chain triggers, but when user B executes the same Z transaction after sometime, then the event raises, but the PC is descheduled automatically and will not run... then the user B again needs to schedule it and access the Z tcode... and the probelm is User A cannot trigger the chain when he executes the PC as it will be descheduled automatically

please sugget