Capacity over load

Dear All,

I saw the capacity evaluation for a work centre in CM 50- The work centre is overloaded on 25.05.2011.

Thereafter i created a production order, scheduled it using backward scheduling-some of the operations of teh order were scheduled on 25.05.2011. On doing the capacity availabilty check, the system gives the message- Capacity available at all work centers.

Shouldn't it have gave the message regarding capacity overload on 25.05.2011 which gets reflected in CM 50??

Also,

what is the user exit to be used to prevent the order release if capacity is unavialble at work centres?

Regards,

Chetan.