Problem in Assembly Processing in Project System

Hello All,

My Client want to implement Assembly Processing. We have configured the system as per SAP Standard. we are testing this in Quality System along with SD & PP Modules. we have template which contain Material WBS Process WBS & Other Cost WBS But we are getting all cost of material and process cost on one Material WBS after Production order confirmation. How can we divide this cost separately for Material & Process WBS.

As SAP Standard Process we maintained activities for different process also but when we tested this we are not clear about the use of these activities. We are not getting any cost or don't have any relation in any way for these activities.

Please Help me about this Assembly Process.


Warm Regards


Not what you were looking for? View more on this topic or Ask a question