Hello,

I would like to konw if a schedulling agreement has been created via edi. Is there any field or any transaction where is indicated so?

Thanks a lot!

Regards,

JMadariaga

Accepted Solutions (1)

Accepted Solutions (1)

Shiva_Ram
Active Contributor
0 Kudos

In t.code VA33, go to menu Goto->Header->Sales tab. Here check the field created by.

Regards,

j_madariaga
Participant
0 Kudos

Hi,

In that field it can be seen who the creator of the schedulling agreement is, but I need a field which indicates if that schedulling agreement has been created via Idoc. There may be a table in which this can be specified.

Thanks.

Regards,

JMadariaga

paul_quinn
Participant
0 Kudos

Hi,

in your title bar "Display scheduling agreement xxxxx", you should have a "Services for Object" icon

If this is not present, you may have to add it to your profile in SU01

(Just set SD_SWU_ACTIVE to X)

If the icon is there, click it

now a small toolbar should appear

If the "display relationships" icon is not greyed out, click it

You should now see all the idocs associated with this scheduling agreement

Hopefully, the first one is the idoc which created the scheduling agreement.

Also, if you just wish to see the last idoc associated with the scheduling agreement

.After you click the Fore Dl Sch tab or the JIT DlSh tab

Click the Dlv Sch Hdr

Then Click the "Curr Idoc" and you will see your current idoc.

kind regards

Paul Quinn

Answers (1)

Answers (1)

former_member303858
Contributor
0 Kudos

Hi,

One other way to find out if the agreement is created by an idoc is to find out the PO no in the agreement ( if you have) or any other no which you feel is available in idoc and agreement both.

go to we09 and put the number in the segment in the search and execute. This will find the idoc from which the agreeemtn is created.

Hope it helps.