I would like to konw if a schedulling agreement has been created via edi. Is there any field or any transaction where is indicated so?
Thanks a lot!
Regards,
JMadariaga
In t.code VA33, go to menu Goto->Header->Sales tab. Here check the field created by.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
in your title bar "Display scheduling agreement xxxxx", you should have a "Services for Object" icon
If this is not present, you may have to add it to your profile in SU01
(Just set SD_SWU_ACTIVE to X)
If the icon is there, click it
now a small toolbar should appear
If the "display relationships" icon is not greyed out, click it
You should now see all the idocs associated with this scheduling agreement
Hopefully, the first one is the idoc which created the scheduling agreement.
Also, if you just wish to see the last idoc associated with the scheduling agreement
.After you click the Fore Dl Sch tab or the JIT DlSh tab
Click the Dlv Sch Hdr
Then Click the "Curr Idoc" and you will see your current idoc.
kind regards
Paul Quinn
Hi,
One other way to find out if the agreement is created by an idoc is to find out the PO no in the agreement ( if you have) or any other no which you feel is available in idoc and agreement both.
go to we09 and put the number in the segment in the search and execute. This will find the idoc from which the agreeemtn is created.
Hope it helps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.