Unable to reset WBS Budgeting status (OPSX)

Dear experts,

I want to reset BUDG status and delete WBS (system status CRTD BUDG).

But when i run OPSX for this project or WBS I get "The following WBS elements are budgeted (status unchanged)"...

Previuosly I made budget updates and did following steps:

1. Budget supplement (CJ37) 500 Eur.

2. Budget return (CJ38) 500 Eur.

So now the budget is empty but as a result the BUDG status is stuck on the WBS and the project (or WBS) is blocked for deletion.

Maybe there are reversing/reposting methods for budgeting documents or something like that, what could help me? (FUNDS MANAGEMENT not installed - FR89)

Please help solving this issue.