on 05-24-2011 1:59 PM
Sir,
As working with dynamic modification rule , we know that next material going to gr is a skip lot,
So for coming lot i want system do not skip the lot , i want system to create a inspection lot
After this lot agian i want to go as per DMR setting
wether it is possible
Faisal
Have you checked T code QDL2 .
Tries to change the level.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I - Change the status of the new inspection plan and use the old one.
2 - edit the plan and remove the DMR until after the next receitp
3 - The inspection lot is always still created. Just use the skip lot inspeciton as you would a normal inspection lot. Just make sure you change at a least one resutl before teh skip lot batch job has a chance to process the lot.
FF
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.