Dynamic modification rule


As working with dynamic modification rule , we know that next material going to gr is a skip lot,

So for coming lot i want system do not skip the lot , i want system to create a inspection lot

After this lot agian i want to go as per DMR setting

wether it is possible



Go to QDl2->n current data->check next stage--->if its skip then change to inspection( like 10 -initial)

once you done with inspection stage change it again to skip ( like 20)

i hope you will explore