Hi Friends,
I am working on operation wise subcontracting.The process is i have 3 operations.The second operation is external operation.
I have 2 raw materials an d one semifinnished and one finished.
I have created BOM for semifinished and finished.
I have created one work center.
I have created routing for both semifinished and finished.
I have created Demand plannning(MD61) for finished product. and run the MRP for semifinished and finished.
Both Orders were released. I have created one dummy Material without nonvaluated.When i released the orders wher can i get perchage requetion number.Please tell me the process clearly.
If you provide the exactprocess i will map with my business process.
Please tell me the steps.
Thanks Venkat
Hi friends,
I am not getting correct answer.
Please tell me.
Thanks
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
To make an operation as externally processed, first assign it a control key that says that it is an externally processed operation. Then you can fill-in purchasing info in its "Ext. Processing" tab. In that tab, select the top-left check-box to make it sub-contracting. There is no need to have a "dummy" material to make an operation externally processed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hy;
His line of reasoning is correct but there are other factors to consider. I recommend that you read this documentation:
http://help.sap.com/saphelp_47x200/helpdata/en/b1/c04ad5439a11d189410000e829fbbd/frameset.htm
I hope that clarifies.
Regards.
Luciano Nóbrega
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kumar.
You will find the purchase requisition number in the operation view of the production order. There is a columns called "purchase requisition".
Please consider that this purch req will be created with "material" = blank so you won't be able to find in EBAN using material number as key. Considering is in the operation detail, i'm not sure but probably you will find it in AFVV/AFVC table.
Regards,
Mauro
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
can u tell me what is used for " one dummy Material without nonvaluated "
Regards
vinod
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.