Daily Work schdule varient

Former Member
0 Kudos

Dear All

Requirement is: if holiday class=1 fallen on saturday then following monday will be half day..

I havr tried to do it through daily work schudule rule (varient).

I put conditon as below.

01 (rule no) If holidays class =1 (for current day) and weekdays = 6 (saturday) then variet B

In daily work schedule i create a half day 8 to 12 and i assign this varient B.

I dont know what else i need to do...we ar using +tive time.

Requirement is: if holiday class=1 fallen on saturday then following monday will be half day..

help me how to do this requirment .

Manjula.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

We do not haveoption to query previous day in selection rule. I think you need to do it through user exit.

Rgds,

Lata

Former Member
0 Kudos

HI Lata,,

I think no need to query on previous day...my requirement is if holiday class =1 fallen on saturday then i have to make half day (8 to 12) on monday. (following monday)

thanks and regards,

Manjula

Former Member
0 Kudos

can any one help?...