Hello gurus,

We run MRP on ECC6.0

Our plants will have one week shut down, so

we need to stop some deliveries being planned in MRP for the week of the shutdowns - all goods inwards will be closed.

What is the best way to achieve it?

The following options I see:

1. The mass changes for all relevant materials u2013 to set MRP type ND (no planning);

2. To do some settings in SPRO u2013 which one(s) ?

3. ?

Thank you!


Hello mr bin.

Requirement is not clear, but if i got your point, you want to avoid mrp proposals (scheduls lines, planned orders) delivery date to fall within a particular week, during whic the factory is not working/receiving material.

The best way to do that IMHO is to close the plant calendar using transaction SCAL, creating a special rules for NON WORKING days with period = factory closing week.

Please consider that if you have more than one calendar ( ie. one plant calendar in plant customizing and one production calendar in production work centers) you need to close both.