Hi,

The requirement is to have different scope for availability check when Standard Sales Order and a Replacement Order (Replacing the goods for free).

In the above scenario, the item category is different, so we can have different requirement type, hence can have different requirement class.

Item category determination is based on Sales document type, but availability check do not have any control at sales document type level.

Scope of availability check can be controlled with the combination of Checking group (material master) and checking rule.

I need clarification here on how we can get different scope of check for the same material.

Clarification on this is highly appreciated.

Regards.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Checking Rule is assigned with Plant also. So if Replacement Order is created from a single Plant then you can achieve the same.

Else if you don't want to run Availabily Check then you can remove the checkbox "Availability" from Schedule Line Category.

Best Regards,