on 05-24-2011 6:31 AM
Hi All,
We are on SRM 7.0 and using application controlled workflow.
We are using the 1 step SC approval workflow WS10000129 (One-step approval of shopping cart). I will be using the task TS10008126 - Approval of shopping cart - Manager role or general task for this. All requests over $100 are to be routed to the manager in the org structure.
I have activated the start conditions in SWB_COND but I dont see any entries in SWi1 after ordering the SC.
Also in BBP_PD I see the following
HEADER I1015 Awaiting Approval
HEADER I1021 Created
HEADER I1038 Complete
HEADER I1106 Shopping cart ordered
Pl let me know if I have missed something.
Regards
Hi,
Check your event linkage in SWE2.. the subworkflow and workflow has to be activated with general task....
Saravanan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The workflow WS10000129 and the task TS10008126 have been activated as General task...
I removed the start conditions and then rechecked the behaviour. Fortunately it worked and the manager was able to approve the SC. Could you shed some light on maintaining the start conditions correctly, so that I can achieve the original behaviour where SCs over $100 can be routed to the manager ?
Regards,
Nikhil
Hi,
Our team here does not have exposure to PCW, hence we are going with ACW. Can you suggest some material from where I can configure standard PCW which suits our requirement?
Also for the time being can you suggest an interim solution for maintaining start conditions using ACW?
Regards,
Nikhil
Hi,
You can find the PCW help in the below link http://help.sap.com/saphelp_srm70/helpdata/en/74/c0256bebb54f1c8dfb519d2908152b/frameset.htm.
Can you please share your start condition ?
Saravanan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.