my scenario is REM,Requirment time is not dispaly in mf50,ie how much time required it is not display in planning table mf50.how it is configure or where is setting itis display required time.
T&R
Hi,
You will be able to see the Avaialble time and time requried in the top of the MF50.
if this is not displayed check in scheduling if you are using the Rate based plg.
BR,
Dsk