Hi ,

Recently we upgraded from SNC5.1 to 7.0.Supplier enters the shipping date in PO worklist and system in turn calculates the Delivery date.This is working fine in Production also.

But after upgrade we found that when supplier enters the shipping date other than requested shipping date by customer then System is not saving the date and in turn when gets published customer requested shipping date is getting transmitted to ECC.

Chnage date is not working.

Thanks and Regards

Raghavendra Pai