on 05-23-2011 10:22 PM
Hi ,
Recently we upgraded from SNC5.1 to 7.0.Supplier enters the shipping date in PO worklist and system in turn calculates the Delivery date.This is working fine in Production also.
But after upgrade we found that when supplier enters the shipping date other than requested shipping date by customer then System is not saving the date and in turn when gets published customer requested shipping date is getting transmitted to ECC.
Chnage date is not working.
Thanks and Regards
Raghavendra Pai
Hi Raghavendra,
First check your validation setting is maintained as below or not:
Validation profile:POC3
Validation check:PO_COPY_CONF_TO_REQ
Status:Active
Validation profile:POC5
Validation check:PO_COPY_CONF_TO_REQ
Status:Active
If it is not maintained then maintain above settings(Normally this setting will be there in standard validation).
Regards,
Nikhil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Raghavendra
In Spro-SNC-Delivery-Due Quantity Calculation-Determine Due Schedule Line Quantities
For the field D/T Due Qty (Conf.), can you check the logic??
Is it S Shipping Date/Time for your supplier and customer BP's
Best Regards
Vinod
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vinod,
I did not get you. My settings in Due Quantityt calculation are
D/T Due Qty (ASN):Shipping Date/Time
D/T Due Qty (Conf):Shipping Date/Time
D/T for ASN in DL: Shipping Date/Time
and one more thing when Supplier reates ASN through Due List for Purchasing Documents system takes the shipping date and Delivery date requested by Customer
Is it possible to populate Supplier confirmed date when Supplier clicks on creates ASN .
Regards
Raghavendra Pai
Hi Raghavendra
I have the below settings
D/T Due Qty (ASN):Shipping Date/Time
D/T Due Qty (Conf):Shipping Date/Time
D/T for ASN in DL: Shipping Date/Time
Relevant PO SL:CONF
Also i have deactivated the validation check
PO_SHIP_AFTER_DELVRY_DATETIME
for profiles POC1,POC2 & POC3
I am able to enter the CDD date as desired, same is transferred to ERP
Regarding Due list query
When you create an advanced shipping notification (ASN) for a purchase order item in the due list for purchasing documents, the system fills the ASN with the data that is currently displayed in the due list for purchasing documents.
and this is requested data, i am not sure how to get confirmed data into due list query, you need to ask any webdynpro developer, like which FM and query it is referring and modify it suitable
You can create ASN for confirmation line in PO details, as it is allowing to store the delivery date now
Best Regards
Vinod