Hi All,
we are using Heuristic SAP002 "Remove Backlog" on the detailed scheduling planning board on a resource.
The problem is that if there is a Gap between operations (lets say between the 2nd and the 3rd) and the Gap is there for a reason. When doing SAP002, the backlog is removed, but also the Gaps between the operations. Is there any sulotion for this?
Thanks for your answers
Hi Arieh,
Are you running SAP002 for resources of all operation or only for resource of first operation?
Are there any maximum or minimum intervals maintained between activities of two operations.?
There is gap between 2nd and 3rd operation because of valid reason is it because of capacity reason? Or what else is that valid reason.
Regards,
Santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
We are using SAP002 by selecting the resource, so it runs on all operations (different prod.orders) that are scheduled on that resource.
There are no maximum or minimum intervals maintained between activities of two operations. The gap is there for a reason, for example production planning wants to finish a prod.order and the next prod.order will start only tommorow, or they do planning for the future but for some period there are no orders yet (MTO)
Thanks and regards
Hi,
As per my understanding what you need is
suppose operation1, operation2 and operation 3 is scheduled in the past(backlog) there is gap of two hours between operation 2 and 3 when they are scheduled in past. Now post running remove backlog heuristic you want system to schedule these orders from current date and also maintain gap of two hours between operation 2 and 3.
Correct me if i have understood it wrong.
If requirement is as above it is not possible with logic with which SAP002 works. It just deallocates orders in pat sorts it with start date and time and then goes on scheduling with current date and insert operation strategy one after another. Two maintain that gap you need to have some custom logic which defines start date of operation considering this gap.
Regards,
Santosh
Santosh Hi
Thank you for your answer. This is excatly how you described the issue. We will try to find a work around or to maybe include a custom Logic as you advised.
Thank you
I have a nother issue please:
If our plant works 7 days a week for a few months and 5 days for a few month during a year. Also, there are shifts involved.
How do you recomend to set it up?
This is what we set up:
1.We created a planning calendar with "no gaps" for 7 days a week (Mon-Sun) each day starts at 07:00 (start of 1st shift)
2. Created Shifts : 3 for Sun-Wed, and 2 for Thu-Sat.
3. Created **** seq. for some reason day number 1 came out to be Fri, Even if in the planning calendar the 1 day is Mon when looking at the capacity profile.
4. Created a cap. variant and assign to the resource.
If the plant come to the period, in which working 5 days a week, should we only change the facroty calendar at the resource?
How do I show the **** in the DS planning board? why we can not see in the board that the day stat at 07:00?
Thanks and Regards
If we look at the live.C time stram the start time of every day is 04:00. not 07:00 as we wanted? in reason why?
Hi ,
If these periods of 5 day working and 7 day working are planned in advance then you can define interval based capacity where you can define from X to Y date its -5day working and Y to Z its 7day.
Regarding displaying of DS board shiftwise I thing it is possible click on diagram part and rightclick you can change to daily , hourly weekly not very sure about shift but I think it should poosible. Rightnow I donot have system access to check
Regards,
Santosh