on 05-23-2011 12:13 PM
Dear Experts
On the Costing view of a Work Center, the work center is assigned to a cost center.
This work center is assigned to an operation in a routing.
The routing is copied when I create a Production Order.
The production order is executed, confirmation and settlement is now carried out.
At what point during this production cycle is this cost center updated?. I mean when are postings automatically made to this cost center to which the work center is assigned to?
How do I view the entries made to this cost center?
When you confirm an operation in the production order (co11n) the CC is credited and the order is debited accordingly. You can see this on the postings of the CC and also on the accounting document that is created when you do the confirmation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.