Entries updated in a Cost Center through Work Center assignment

Dear Experts

On the Costing view of a Work Center, the work center is assigned to a cost center.

This work center is assigned to an operation in a routing.

The routing is copied when I create a Production Order.

The production order is executed, confirmation and settlement is now carried out.

At what point during this production cycle is this cost center updated?. I mean when are postings automatically made to this cost center to which the work center is assigned to?

How do I view the entries made to this cost center?

Former Member
Former Member replied

Hi,

Check S_ALR_87013611 report.