Modifiable Request Status after changing SID

Former Member
0 Kudos

Hi All,

I need to change DEV Systemu2019 SID but there is some modifiable change requests (There are many records in TLock Table). DEV System is the Transport Controller.

Should all change requests be released before changing SID or System Copy process doesnu2019t related to this issue.

Is there any possibility for change request loss during this process?

Any Idea will be greatly appreciated.

Thanks in advance,

Sanaz.

Accepted Solutions (0)

Answers (1)

Answers (1)

markus_doehr2
Active Contributor
0 Kudos

There is no general procedure of changing a DEV system with open change requests. you could export (release) them and re-import them to the new system. You need though to manually import them to QA/PRD after that.

Markus

Former Member
0 Kudos

Thank you for the reply.

I have done a test scenario as follows:

- SAP Fresh Installation

- Restore DEV DB

- System Copy

Now there is no record in TLOCK table.

Does it mean that I had to release all modifiable requests before this scenario?

Any idea regarding this issue will be greatly appreciated,

Sanaz.