service order internal activity cost were not calculated

Former Member
0 Kudos

Dear All,

Hi, I created one service order in iw31 t.code, in this order i entered work center , activity type, work duration. but i am not getting the internal activity plan and actual cost. I am getting the only external plan and actual cost.

I maintained the activity price in kp26, i assigned the cost center to work center. Some times in service order level i am getting the below error:

Missing work center formula,

Any body please tel me the work center formula steps in each tab wise for service

Thanks & Regards,

Reddy

Accepted Solutions (0)

Answers (1)

Answers (1)

ajaycwa1981
Active Contributor
0 Kudos

Hi

Go to CR02 (work center master) and enter the formula in the work center

Ask your PP or PM consultant to do this