on 05-21-2011 7:07 PM
Dear all,
My user created a grn entry for STO using the delivery number X ; later he discovered he should have used delivery number Y.
So he cancelled the Grn , by using STO number (of delivery X) instead of delivery number he entered Invoice Number. Now when i try to do the GRN for Delivery X , it is not possible as Delivery X has not been updated. Stock is showing in transit for the PO(STO) number.
Please help me in resolving this issue.
regards
shashank.
Hi Shashank,
Cancellations shall normally be done by trs MBST or MIGO with the option "cancellation" - reference to the original material document is required. If your user used one of these options you wouldn't have a problem.
Therefore my suggestion now is that you cancel the user's cancellation document (using MBST or MIGO with the option "cancellation"), then cancel the original GR the same way.
BR
Raf
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.