I want know Which time integration happen with PM & MM
Regards,
Ram Rathode
Hi,
1 Non stock material(and servises)- from PM order generates PR, then PO. While GR costs booked to PM order.
2 stock material- from PM order generates reservation,material can be issued to the order against this reservation