Dear PP experts.
we created plan in MD61 for 100 materials and MRP carried out with lead time scheduling.
Now we want to check for all the planned orders scheduling dates as per operatiions wise collectively.
where can we see,, , individually we are getting in display planned order
Please suggest
Regards,
srihari.M
Edited by: Srihari.M on May 21, 2011 3:09 PM
Hi,
There's 3 possible solution.
1st - Create Customize report with planned order table
PLAF - planned order table.
2nd - Goto COOISPI and display all the plan order with the selection that you wish enter the plant code & then execute.
3rd - MD16 Collective Display of Planned Orders report.
Thank you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.