Control WBS Structuring after Release of WBS

former_member213716
Participant
0 Kudos

Dear Expert,

I am trying to control the WBS Structuring after the project release through the User Status, so that no one can change the structure of Project by removing the WBS or by adding new WBS.

But i am not getting any business transaction control in OK02 to control the creation of WBS structure...

I find the below mention 3 transaction control but this will not serve my purpose..

Planning activities

Change WBS number

Change structure

Accepted Solutions (0)

Answers (4)

Answers (4)

former_member213716
Participant
0 Kudos

Thanks , its done

Former Member
0 Kudos

In addition to what Puneet has mentioned the Change Structure transaction should work. Forbidding this transaction won't allow to change the Project Structure. Try it out by creating a new project. It works for me.

Former Member
0 Kudos

Hi,

Activate the object type project definition and WBS element. Try using 'expand structure' and 'delete element'.

'Expand structure' will restrict to add further WBS elements. (at the project level)

'Delete element' will restrict deletion of WBS element (should be individually updated at the WBS element level).

Hope this supports your requirements.

Regards,

Punith.

Former Member
0 Kudos

Hi,

I believe you can achieve this by having user statuses and authorisation control.

Pramod