Hi, good day
If somebody know about, how can I do to make the choice Batch management at MM01 is only at the Plant and not in general.
That is, a material is with Batch management in a Plant and another Plant the same material without Batch management.
If anyone has an idea about this, please anything would be helpful
Hi,
Batch numbers can be unique at the following levels:
1-At plant level
2-At material level
3-At client level for a material
If you choose plant level, the batch number is unique in conjunction with the respective material and the plant. If you choose material level, the batch number is unique together with the material. At client level, the batch number is unique in the whole client.
Plants with batch status management
Activities
To select the plants in which status management is to be active, proceed as follows:
1. Set the Batch status management indicator for those plants in which batch status management is to be active.
2. Save your settings and choose Back.
3. Choose Batch status management -> conversion
4. If necessary, carry out the conversion in test mode first.
Thanks & Regards,
Bijay Pradhan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please check Batch status Management in IMG and also check if batch management check box is checked in purchse view in material master.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Yes, it is possible only for whole plant not for a particular material in a plant. if it is active at a plant level then system will ask for batch.
Batch Management can be activated in three levels. They are
1. Client Level
2. Plant Level
3. Material Level
At plant level, the batch number is unique in conjunction
with the respective material and the plant.
At Material level, the batches are unique at material level, that is, the batch is independent of any plant. The same batch
number can also be assigned to another material.
At client level, the batch number is unique in the whole client. It indicates that batches are managed uniquely for
exactly one material, that is, independently of the plant, the same batch can exist only once for all materials.
Example
a) Plant 1000 item code A Batch 1
b) Plant 2000 item code A Batch 1
IMG --> Logistics General --> Batch Management --> Specify Batch Level and Activate Status Management
Hope Help U !!!
Regards,
Pardeep Malik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.